This week features several major milestone concrete pours, including the final area of Building 9 level 1, forming the parking pavilion and the edge of the central plaza, The first section of slab on grade at building 8, the Building 4 dining hall foundations, and more.
Building 4 level 3 MEP.
Columns and walls have been poured in the final area of Building 6 level 2-3.
Building 4 level 4.
Central plaza from Building 4.
Building 4 upper coutyard.
Building 4 lower courtyard.
Building 4 from Building 6 level 1.
Building 7. The Buildings all have signs now to reduce worker confusion.
Building 7 fine grading in preparation for slab on grade.
Building 7 rebar and edge forming in place for slab on grade pour.
Building 9 level 1 at the pavilion is ready to be poured.
Building 9, level 3 area 1 freshly poured.
The third area of Building 9 level 3 is being formed.
Looking across the Building 9 North courtyard at level 3.
View of the new Fire Station 15 from Building 9 level 3.
Building 9 level 3 and Building 4 in the distance.
The final Building 9 level 1 pour will bring the underground parking excavation back up to the plaza level.
Crews begin pouring concrete at Building 9 level 1.
Concrete pour at the pavilion over the parking entrance at Building 9.
A concrete pump is stationed on Hoover St., forcing a lane closure.
The first Building 8 slab on grade pour is in progress.
Crews pour the first slab on grade section at Building 8.
Work continues rapidly in preparation for the Building 8 area two slab on grade pour at the electrical rooms.
The top of the ramp at the Building 9 level 1 concrete pour is placed.
Concrete pour continues at Building 9 level 1.
Steel anchor bolts in the dense reinforcing at Building 9 level 1.
Rebar in place, ready for concrete at the Building 4 dining hall foundations.
Building 4 dining hall rebar.
Plaza from Building 4.
Simultaneous level 1 pours on Buildings 8 & 9.
Building 4 upper courtyard.
Building 9 level 1 pour at the pavilion.
Shoring at Building 4 level 4.
Building 9 underground parking ramp.
Building 1 fine grading in preparation for slab on grade.
Back side of Buildings 9 & 4.
View across the street to the Kaufman Dance Center under construction on the main USC campus, from Building 6 level 3.
Old Fire Station No. 15 from Building 6 level 3.
Scaffolding is erected around the old Fire Station No. 15.
The old Fire Station No. 15 with tower crane #3.
Building 6 level 3.
Completed Building 8 slab on grade in area 1.
Building 8 slab on grade construction joint at a column blockout.
Shoring going up for Building 8 level 2.
Underground MEP work continues in the Building 8 electrical rooms.
Paseo between Buildings 7 & 8.
Building 7 prepares for its first slab on grade pour.
The final (roof) level of Building 4 is being formed.
Corirdor in Building 4 level 2.
Hole in the Building 4 level 2 floor slab above the electrical rooms. It’ll be filled in a couple weeks.
Building 9 from Building 4 level 2.
The corner of Building 4 level 2 frames the view towards Building 9.
Building 9 and its parking pavilion, and the central plaza.
Building 4 level 2 corridor.
Building 4 dining hall, with the footings complete.
Building 4 level 4 North wing.
Reshoring has been removed from Building 4 level 4 where the low roof above is complete.
View across the future Building 4 dining hall at level 4.
View across the Building 4 upper courtyard at level 4.
Metal stud layout preparation has begun on Building 4 level 4.
Shoring in Building 4 level 4.
Building 6 level 3 area 3 is being formed.
The first section of Building 6 level 3 has been poured.
Building 4 south face.
Building 4 south face. The first sections of precast brick panels will be installed here next week.
Building 4 residential lobby.
Storefront at the Building 4 residential lobby.
Shear wall at the Building 4 residential lobby entrance, which will soon feature an arched opening.
Building 4 residential lobby.
Building 4 southern face, which will receive the first precast brick panels next week.