All buildings are now at final slab on grade stage. Building 1’s structural steel erection has commenced and should be complete within a couple of weeks, as the five concrete buildings continue rising. The Building 4 roof concrete has been finished, meaning that the first building is officially topped out for concrete.
Formwork installation continues in the Building 4 dining hall.
Plumbing for a residential bathroom in Building 4.
The freshly-poured roof of Building 4.
Building 4 high roof looking toward the dining hall and low roof.
View to downtown from the roof of Building 4.
Building 4 across the upper courtyard at the roof.
Rebar column cages are installed up to level 5 at Building 9.
Precast panel bases have been poured around the perimeter of Building 1.
First half of the slab on grade at Building 1 has been poured.
Building 9 at the future Trader Joe’s on the corner of Hoover & 32nd.
Freshly poured slab on grade at Building 8 area 2.
Slab on grade area 2 at Building 8 is complete.
Paseo between Buildings 7 & 8.
Building 6 & Building 9.
The first installation of precast facade panels is complete and ready for architectural review.
A concrete pump pours concrete into the columns for the Building 4 dining hall.
Building 4 and the north wall of its dining hall.
MEP penetrations through the freshly-poured Building 1 slab on grade.
The slab on grade concrete is complete at Building 1.
Site utility work between Buildings 9 & 1.
Building 9 North courtyard.
Level 3 concrete is complete on Building 9.
Dense moment-frame-column rebar cages for Building 9.
Buildings 7 & 8 from Building 9 level 3.
Building 9 parking pavilion.
Methane barrier installation at Building 8.
Future plaza at Hover & Jefferson.
Building 8 storefront along Hoover St.
Building 8 level 2 at the North courtyard.
Building 4 from Building 8 level 2.
MEP layout has begun for level 2 on Building 8.
Building 7 from Building 8 at level 2, where the open courtyard look across the paseo below.
Building 6 and onsite offices from across Jefferson Boulevard.
Building 9 and the pavilion, where the elevator shaft to the parking below is under construction.
The first few steel columns are visible at Building 1.
First four steel columns installed on Building 1.
Building 1, where steel erection has begun.
Steel beams staged for erection at Building 1.
MEP over the loading dock in Building 4.
Metal door frames fill the electrical rooms, loading dock, and all other available spaces in Building 4 as they’re staged for installation.
Future food court in Building 4.
Formwork for the north wing of the Building 4 dining hall.
Building 4 and its tower crane.
Southwest corner of Building 4, where the first staircase has been installed.