Structural steel erection is now complete at Building 1. With Building 4 topped out on concrete, the remaining buildings are quickly rising, with Building 9 level 5 being framed out most recently. Precast facade panel erection is starting to pick up speed at the old Fire Station No. 15 will be moved offsite in just under a month!
The old Fire Station No. 15 continues to be dismantled.
Precast facade panel progress on Building 4.
The awkwardly-shaped panel is the location of a tall pointed arch that marks the dining hall courtyard access point.
Building 6 is catching up to Building 4.
Building 8 south courtyard on level 2.
Looking across the Building 8 bridge at level 2.
Building 8 level 2 south wing, looking toward campus.
Building 8 level 2 along Hoover St.
Steel embeds for precast facade panel anchorage, on the south face of Building 8, where utility work is ongoing in the future plaza.
Rebar marks the wall and door between the corridor and the courtyard on the south side of Building 8.
Building 8 south courtyard.
The Building 7 & 8 courtyards are open to each other across the paseo; the Building 7 level 2 area 2 concrete pour is finishing up.
Paseo between Buildings 7 & 8.
Building 9 now rises four stories above the plaza pavilion.
Building 9 at the parking ramp.
Ramp to parking under Building 9.
Building 9 storefront along Hoover St.
Building 1 structural steel has been completed.
The Building 1 steel visibly slopes toward the center of the building.
Building 1 structural steel at the cooling towers.
Building 1 structural steel at the cooling towers.
Building 1 currently feels very open, but it will soon be full of heavy CMU walls.
View of the new Fare Station No. 15 through Building 1.
Community room space in Building 1.
Building 1 towards Buildings 4 & 9.
Building 1 steel.
Building 9 from the far back corner of the site.
Facade mockup for the Fertitta Hall project, which is also being built by Hathaway Dinwiddie Construction (their site is extremely constrained).
Wall sheathing and brick assembly for Fertitta Hall.
Decorative stormwater drainage pipe on the Fertitta Hall mockup.
Precaast arch detail on the Fertitta Hall mockup.
Future maintenance yard outside the Building 4 dining hall kitchen.
Formwork for the Building 4 dining hall walls.
The huge arched opening in the dining hall has been framed out.
Building 4 dining hall, with the three-story-tall arched opening formwork.
Formwork for a dining hall wall, with blockouts for the main entrance doors.
Building 4 dining hall.
Stairs and precast panels on Building 4.
More precast panels on Building 4.
Residential lobby in Building 4.
Future storefront line at the Building 4 south facade.
A steel embed for a precast facade panel, with the Building 4 dining hall formwork in the background.
Connection detail for two precast panels, bolted into the steel embeds cast into the main concrete structure.
Building 6 from Building 4 level 3.
Precast facade panel connections at a shear wall.
Building 4 level 3 corridor.
A crane prepares to lift more precast arch panels from a truck.
Residential units along the facade of Building 4.
Building 4 level 3 corridor.
Looking through a laundry room to the courtyard in Building 4.
Rebar for CMU planter walls in the Building 4 upper courtyard.
Building 4 upper courtyard.
Central plaza to the Trousdale Paseo from Building 4.
The top of the wall is now visible on the dining hall formwork, as rebar is filled in around the massive arched openings.
Smaller walls for the Building 4 dining hall.
Building 4 dining hall serving area and kitchen.
Looking through a kitchen window to the lower courtyard at Building 4.
Building 9, formed through level 5.
North courtyard in Building 9 from level 3.
Shoring for level 4 in Building 9.
Building 1 from Building 9 level 3.
Massive spaces to be filled with residential units in Building 9 on level 2.
Building 9 level 2.
Looking out to the courtyard at Building 9 level 2.
Building 8 from Building 9.
Building 4 with the base for its tower clearly visible at center, from Building 9.
Reshores in Building 9 at level 2.
Building 9 pavilion, with the CMU elevator shaft, round column forms, and more.
Central plaza from Building 9.
Detail view of half-brick pilaster at the edge of a precast arch facade panel for Building 4 level 1.
Lounge in Building 4.
Old Fire Station No. 15 at the end of the week, with part of its facade and the flagpole now removed.
Bridge between the two sections of Building 8.
Leave a Comment