Sherwood Highway 99W Pedestrian Bridge Span Erection

One year into construction, Sherwood’s Bicycle and Pedestrian Bridge over Highway 99W came to life in a matter of weeks when the bridge spans were installed this spring.

Bridge Span Assembly

Each of the five bridge spans is simply supported. This means that they are structurally independent and self-supporting. The upright tied arches and inverted arch trusses are all biaxially symmetrical and can be lifted from four symmetrically located points. These trusses were assembled on site and in the Thompson Metal Fab shop in Vancouver, WA prior to erection to minimize road closures and traffic impacts.

Span 5 – March 8, 2025

The main bridge span over Highway 99W was first to be installed, on March 8, 2025. Extensive planning went into the highway closure and detour to Elwert Rd, beginning during the bridge design and continuing through the work in collaboration with ODOT, Washington County, the City of Sherwood police department, and other local partners. While the plans called for a full weekend closure from 9pm Friday through 5am Monday, crews completed the work and reopened the highway in just 24 hours. Span 5 is the largest on the bridge with a 194-foot span and 39-foot height at the work points. All spans have their trusses tilted outward at a 5-degree angle, creating a unique form with apparent shape-shifting across viewing angles.

At the tightest point along its journey, span 5 fills the full diagonal width of 99W/Elwert/Sunset intersection.

Spans 4 & 3 – March 22, 2025

With concurrent assembly work, the next two bridge spans were ready to be installed just two weeks later. This time, Highway 99W remained open while Kruger Rd, Elwert Rd, and the roundabout were closed to traffic.

As the crane prepares to de-rig, the scale and alignment of the bridge project become much clearer to the public.

Spans 2 & 1 – May 17, 2025

Much of the work to fabricate the final two bridge spans was initiated following erection of spans 3 & 4, resulting in an eight week gap to this final step. This allowed onsite work to shift focus to pouring concrete decks and east approach retaining walls to maintain the overall schedule. With a similar roadway closure to the previous two spans, the bridge achieved its final form in a seamlessly choreographed effort.

The five bridge spans, with the crane holding span 1, from the construction staging yard.
The Sherwood High School baseball field’s berm offers broad views of the bridge galloping through the trees.
Summary of the span lengths, heights, and aspect ratios of the bridge spans.

Timelapse Videos

ACMS NW is providing daily onsite inspection services for this project and collaborated with Stratoscape to produce aerial photography of the bridge span erections for all five spans.

Construction will continue with completion of the east and west approach ramps, concrete bridge decks, architectural and pathway lighting, railings, and landscaping in the coming months. The bridge is scheduled to open to bicycles and pedestrians this fall.

Leave a Comment

Your email address will not be published. Required fields are marked *